Summary
Selectmen scheduled workshops on winter-roads contractor expectations, approved asking a town contractor to fill washed gravel near 103 Main St (if funds), and authorized painting of 25MPH signs and crosswalks, with contingencies for alternate contractors.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
The board reviewed winter-roads complaints and scheduled a contractor workshop for April 9, 2025 to address issues including clearing near doorways. Ray Hodsdon moved to have 'Charlie' fill washed gravel near the culvert at 103 Main St if funds permit; Matthew Patneaude seconded and the motion passed 3-0.
For road-painting, Timothy Derouche moved that the town ask Danny Bulger to paint all 25MPH signs and crosswalks and, if Bulger is unavailable, to ask Richard Cox provided he carries appropriate insurance. The board also discussed summer-road plans including speed-hump installation by Nick Pierce and the use of a mobile speed sign. Separately, the board approved paying stipends up to three months in advance.