Residents press safety questions after Lineage says facility will hold ~25,000 lbs of ammonia
Summary
Lineage Logistics disclosed a design refrigerant charge of roughly 25,000 pounds of anhydrous ammonia for its proposed Olathe cold-storage facility; residents and some commissioners pressed for more documentation on RMP/PSM compliance, emergency response, and lessons from a 2024 Lineage fire in Washington.
Get email alerts on the Hazmat Safety topic
No spam. Unsubscribe anytime.
Lineage Logistics told the Olathe Planning Commission that the refrigeration system for the proposed automated cold-storage facility would be a closed loop that uses anhydrous ammonia and that the largest receiver will hold roughly 25,000 pounds of ammonia. Jim Romine, Lineage vice president of construction and design, said the vessel operates at roughly 120–150 psi, has relief valves and is protected by an extensive preventative‑maintenance and testing program.
"We're going to have around 25,000 pounds," Romine said during the presentation, a declaration that triggered questions from commissioners and residents because federal EPA and OSHA programs apply at lower regulatory thresholds. Romine described compliance practices the company follows — periodic preventative maintenance, leak detection, relief-valve replacement cycles and a process hazard analysis conducted before system commissioning.
Residents and several commissioners repeatedly asked for specific RMP/PSM documentation and local emergency‑response planning. Commissioners requested a formal response from the Olathe Fire Department on equipment and response times; the city relayed a deputy chief’s estimate of roughly six minutes, and staff said the facility’s RMP will be sent to the local emergency planning committee for coordination. Local commenters cited the 2024 Findlay, Washington Lineage facility fire and asked whether Lineage had changed its corporate safety practices: the company said it had reviewed older facilities and focused upgrades where needed but did not provide a detailed post‑incident report at the meeting.
The commission asked the applicant to provide more documentation on safety protocols and on how emergency notifications and evacuation would be executed if an off‑site ammonia release occurred. The item proceeded without immediate closure of those questions; commissioners later voted on the rezoning and the motion failed on a 2–5 roll call.