Holiday Hills says sewer work about 20% complete; no winter paving planned
Summary
President Giles told trustees the sewer project is roughly 20% complete and that residents should expect exposed gravel and road cuts through spring; paving will not occur until warmer weather.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
President Giles reported at the Dec. 11 meeting that the village sewer project is about 20% complete and that residents have asked about exposed gravel and road cuts. He told the board that those conditions will likely remain until spring and that the contractor will not pave until weather allows.
Giles urged patience and said the village expects visible roadwork until the project progresses further. No formal motion was associated with the update; it was delivered as part of the president’s report.