Engineer: AMD Phase II nearing completion; Chub Run to start Nov. 1, 2025; Phase IV forcemain awaits WVDEP clearance

Town of Nutter Fort Council · September 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The engineer reported Phase I AMD pay-application comments addressed, Phase II final design submitted with 28 of 34 ROWs secured and OSM environmental clearance outstanding, Chub Run scheduled to start Nov. 1, 2025 with a change-order for time extension expected next month, Phase IV forcemain pending WVDEP clearance, and preparations underway for an Edison retaining-wall engineering contract.

The engineer's written report covered multiple infrastructure projects. Phase I AMD pay-application comments have been addressed and may require a special meeting to approve a requisition depending on comment approval timing. Phase II AMD final design was submitted by Sept. 1, 2025; 28 of 34 rights-of-way are in hand and the project is awaiting environmental-assessment clearance from the Office of Surface Mining (OSM) before going out to bid, expected by year-end if clearances arrive.

The Chub Run project has a projected start date of Nov. 1, 2025; the engineer indicated a change order for a time extension will be presented next month. Phase IV forcemain work is awaiting environmental clearance from the West Virginia Department of Environmental Protection (WVDEP) and all documentation has been provided. An engineering contract is being prepared for the Edison retaining wall project.