Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Projects topic

No spam. Unsubscribe anytime.

Engineer reports progress on Phase II AMD/AML and delays on Chub Run sewer extension

Town of Nutter Fort Town Council · October 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineer reported ROWs secured for Phase II AMD/AML (28 of 34), environmental assessment submitted to the Office of Surface Mining on 10/23/25 with intent to bid by year end; Chub Run sewer extension contractor start was scheduled for Nov. 1 but likely to be delayed until end of year; Phase IV sewer project awaits PSC and DEP approvals to connect to Sandy's Hardware station.

The town's engineer submitted a written report and highlighted multiple infrastructure projects. For the Phase II AMD/AML project the engineer said 28 of 34 right-of-way easements have been secured and that the environmental assessment was submitted to the Office of Surface Mining on Oct. 23, 2025; the engineer indicated the project was aiming to go out for bid by the end of the year.

On the Chub Run sewer extension, the contractor was scheduled to begin around Nov. 1 but the engineer cautioned the start would likely be delayed until later in the year. The Phase IV sewer project remains contingent on approvals from the Public Service Commission (PSC) and the Department of Environmental Protection (DEP) for a connection to the Sandy's Hardware station.