Board reviews paving bids and pauses bus‑barn work after EPA soil testing is scheduled

A-C Central CUSD 262 Board of Education · September 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The facilities director reported two paving bids and said the EPA will test soil near the bus barn for potential contamination from a historic underground tank; staff proposed splitting the teacher parking lot work from bus‑barn work to avoid delays.

Facilities staff told the board the district received two bids for paving work: Ron Furman & Sons (low bidder) and Kenny Contractors. Staff recommended proceeding with the teacher parking lot and using an addendum to delay bus‑barn paving until EPA completes soil testing near an historic underground tank.

"They are coming out to the site to test some soil…just at the bus barn," the facilities representative said, adding the district was told the EPA would visit on Sept. 26. Staff proposed a contract addendum to keep the teacher parking lot on a tighter timeline (completion target Oct. 31) while pushing bus‑barn paving into November if EPA testing requires remediation or further review.

Board members asked about alternates and costs. Staff described a $56,000 concrete alternate for the teacher lot (bringing the bid to about $420,350) and discussed life‑cycle tradeoffs: concrete lasts longer (40+ years) versus asphalt (15–20 years with sealcoat maintenance). Members pressed for more detailed line‑item breakdowns from bidders and for coordination with planned HVAC work and other bond projects before committing major bond funds.

The board later voted to table final action on the staff parking lot and bus‑barn bids pending more information about HVAC scope, grading breakdowns, and EPA results.