Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Public Works topic

No spam. Unsubscribe anytime.

Council approves $115,776.15 partial payment for downtown paving; rapid‑flashing beacons delayed, staff proposes temporary safety signs

Lindstrom City Council · June 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff recommended and council approved a $115,776.15 partial payment to Windberg/Winberg Companies for downtown parking lot paving; the rapid‑flashing beacon installations are delayed (supplier coding/coating issues), and staff proposed temporary pedestrian warning signs for upcoming events.

Public works staff told the Lindstrom City Council the downtown paving work is complete and the remaining work is two days of striping; after review of progress staff recommended a partial payment to Windberg/Winberg Companies in the amount of $115,776.15. The council moved the payment and approved it by voice vote.

Staff also reported a delay in delivery of the rapid‑flashing beacons because of a supplier coding/coating issue and said installation might not happen until late July. To protect pedestrians at upcoming events (including midsummer and Carl Oscar Days), staff proposed temporary crosswalk/warning signage instead of closing sidewalks. Staff said they will have crews clean up and stage traffic control equipment after striping and before the weekend events.

Councilmembers raised a localized standing‑water concern on a 3x3 area remaining after milling; staff recommended leaving that small area alone because patching now could look like a patch and age poorly. Public works also described plans for a seal‑coat maintenance fund to extend pavement life and noted annual allocations are already in place.