Board ratifies Shasta High parking change orders and approves architect agreement for field lights

Shasta Union High School District Governing Board · February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board ratified change orders increasing the Shasta High overflow parking contract by $22,664.05 and approved an architectural services agreement with Nichols, Melburg & Rossetto to investigate multi‑campus field lighting and repairs ahead of bidding.

The Shasta Union High School District Governing Board approved Change Order Numbers 1 and 2 for the Shasta High School overflow parking lot, ratifying a net contract increase to Lamb Unlimited of $22,664.05. Associate Superintendent David Flores said striping and directional arrow work was redone to better accommodate traffic flow and that the City of Redding changed driveway slope requirements, necessitating additional work; Flores added the project’s overall cost remains below the original projection.

Separately, the board approved an Architectural Services agreement with Nichols, Melburg & Rossetto (NMR) to perform the investigation and findings phase for districtwide field repair and lighting (RES. 26-033). David Flores said the firm will assess electrical supply, irrigation and field conditions for varsity softball and baseball fields to allow the district to prepare a proper bid package; the district will return with a contract for construction work after the investigative phase.

Speakers referenced in this article: David Flores (Associate Superintendent of Business Services).