Trappe approves $6,875 repair, authorizes $73,992 sewer main lining scope funded by ARPA
Summary
The council accepted Talbot Land Management’s $6,875 quote to repair the wastewater treatment plant ditch and approved Livingston Septic’s $73,992 scope to line 1,016 feet of sewer main and reinstate 22 laterals, funded from a prior $75,000 award of ARPA funds.
Get email alerts on the Sewer Project topic
No spam. Unsubscribe anytime.
The Trappe Town Council on April 2 accepted a $6,875 bid from Talbot Land Management to repair a ditch and entrance at the wastewater treatment plant and approved a scope of work from Livingston Septic for an ARPA-funded sewer main lining project.
Water Superintendent Shawn Lane presented price options: “Quote 1 is from Good Life Property Management for a total of $8,975.00 and Quote 2 is from Talbot Land Management for a total of $6,875.00.” Councilors voted to accept Talbot’s lower bid. Administrator Erin Braband then summarized Livingston Septic’s proposed scope: installing 1,016’ of 8-inch fiberglass pipe from manhole 3 to manhole 7 and reinstating 22 laterals for $73,992.00. The Council had previously awarded $75,000 for the project and Commissioner Rose Potter moved to approve Livingston Septic’s scope; the motion passed unanimously.