Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure Repair topic
No spam. Unsubscribe anytime.
Council approves $188,171 engineering design contract for Hillbreath Drive sewer replacement
Summary
The town awarded Baxter & Woodman a design contract for the Hillbreath Drive gravity sewer main replacement project ($188,171). Staff said the existing line is severely deformed, has caused overflows, and will require trenching and soil replacement; council approved the design contract 5-0.
Get email alerts on the Infrastructure Repair topic
No spam. Unsubscribe anytime.
Council reviewed a proposed engineering services agreement with Baxter & Woodman to design the Hillbreath Drive gravity sewer main replacement at a cost of $188,171. Staff described multiple overflows and a pipe configuration that prevents camera inspection because the line is "wavy" and severely deformed; the project will require excavating the roadway and replacing surrounding soils to properly seat a new pipe.
Director Crockett said the pipe segment sits over an old landfill and acknowledged the work will likely require road repaving: "It's really bad and it's built on top of an old, landfill," he said. Council member Rivera and others asked about soil contamination testing and potential costs for hazardous-material handling; staff said soil analysis and dewatering precautions are included in the scope and that costs could increase if contamination is detected. Council approved the design CSA and authorized the town manager to execute the agreement, 5-0.
