Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Infrastructure topic

No spam. Unsubscribe anytime.

Inspection finds rust and blisters in Well #4 tank; painting recommended within 3–5 years

Notus City Council · March 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported Well #4 reservoir tank is 26 years old with rust and internal blisters; the contractor recommended interior work within three years and exterior painting within three to five years, and the city is seeking repair estimates.

Public Works Supervisor Tyler Martin told the council that Well #4 reservoir was cleaned and inspected and that the tank showed rust on the top and blisters on the inside. The tank is 26 years old; the inspecting company recommended interior rehabilitation within three years and exterior painting within three to five years.

Martin said he has video of the inspection and is seeking repair estimates, and he expressed a preference to complete necessary work within two years if possible. The report has been sent to DEQ as part of ongoing wastewater and water-system communications related to recent fire-related changes.