City engineer: lagoon report submitted to DEQ; seepage test planned for September

Notus City Council · April 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Engineer Antonio Conti said the preliminary engineering report for Notus’ lagoon will go to the Idaho DEQ for approval; construction design for a UV treatment system will follow and lagoon seepage testing is scheduled for September when the lagoon is fuller.

City Engineer Antonio Conti told the council that the city’s preliminary engineering report for the wastewater lagoon is being submitted to the Idaho Department of Environmental Quality for review and approval. Conti said that, after DEQ approval, the construction design for a UV disinfection system will be submitted for approval.

Conti also reported that lagoon seepage testing has been approved and is scheduled for September when the lagoon will be fuller, which officials said will provide better test conditions. No construction work was authorized at the April 20 meeting; staff will proceed through the DEQ review and subsequent design steps.