Engineer: A&J low bidder at $840,775 for 2026 concrete program; Ridgebury work begins
Summary
City Engineer Mader reported the Ridgebury project began with eastbound traffic maintained, said A&J Cement Contractors was the low bidder for the 2026 Concrete Program at $840,775 (about $35,000 below estimate), and that the Kenbridge sewer project may be eligible for 100% county reimbursement pending confirmation.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
City Engineer Mader updated council on several capital projects and procurement results at the June 9 meeting.
Mader said residents continue to raise concerns about restoration work related to an AT&T project and that staff are monitoring and coordinating with the contractor on necessary lawn and landscaping restoration. He announced the Ridgebury project began yesterday with eastbound traffic maintained during construction.
On the 2026 Concrete Program, bids were opened last Thursday and the low bidder was A&J Cement Contractors at $840,775 — roughly $35,000 below the engineer's estimate. Mader said he is awaiting county confirmation on possible 100% reimbursement for the Kenbridge sewer project and hopes to have that project ready for bid by the end of the month. He also said retention basin inspections will be conducted citywide over the next two to three months and advised residents to contact his office before repairing damaged sprinkler systems so crews can inspect alleged contractor damage.