Bond County approves North Mulberry Grove Road patching; Red Ball Bridge design reaches 60%

Bond County Board · June 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The county adopted Resolution 06-02-26-01 to authorize partial-depth patching of North Mulberry Grove Road and heard a status update that the Red Ball Bridge design is about 60% complete, allowing preliminary final plans to begin.

Bond County approved Resolution 06-02-26-01 authorizing partial-depth patching of North Mulberry Grove Road on June 2. The motion to adopt the resolution was made by Jeff Rehkemper and seconded by Jacob Rayl; the roll call vote was 5 ayes, 0 nays.

Highway Engineer Mike McCormick told the board the Red Ball Bridge design submittal is approximately 60% complete and that the consultant can begin preparing preliminary final plans. No construction timeline or contract award was reported at the meeting.