Swift Current Energy summarizes Triple Black Diamond Solar — 2,125-acre project includes battery storage and community benefits
Summary
Applicant Swift Current Energy presented technical and community material for the Triple Black Diamond Solar project, citing a stormwater study, an IDNR finding of no protected-species impact, and a Community Benefits Agreement that includes $40,000 for the Weldon Fire Department.
Get email alerts on the Project Overview topic
No spam. Unsubscribe anytime.
At the Aug. 20 DeWitt County hearing, Matthew Cate, attorney for Swift Current Energy, and company representative Daniel Sheehan distributed a project packet and outlined the Triple Black Diamond Solar proposal.
Sheehan said the project would occupy approximately 2,125 acres and include a battery storage system. He told the Board that a Waiver of Extra Territorial Jurisdiction Agreement with the Village of Weldon was filed with the application and that a stormwater study "found the project will cause no increase run off as currently designed." He also said the Illinois Department of Natural Resources concluded "there would be no impact on protected species." The company offered $40,000 to the Weldon Fire Department for a UTV with firefighting equipment, an item the local fire board was set to consider.
The applicant team introduced specialists covering environmental review, construction, development, cyber security, property-value analysis and engineering. The packet included a Frequently Asked Questions page addressing revenue distribution questions such as school-district impacts.