Committee reallocates $85,000 to position Vernon Acres generator project for FEMA match
Summary
Committee agreed to reallocate an existing $85,000 allocation to support installing a generator at Vernon Acres and asked staff to pursue roughly $86,000 in FEMA/state funding to cover the balance of a roughly $162,000 project; the motion passed and staff will adjust applications pending a grant decision.
Get email alerts on the Emergency Preparedness topic
No spam. Unsubscribe anytime.
Amy Oliver (Resource and community development, speaker 7) told the committee FEMA/state officials indicated about half the generator cost (~$86,000) could be available; coupled with $85,000 already allocated in local funds, the county would have enough to install a new generator at Vernon Acres.
Committee members debated alternatives, including connecting to the sheriff's generator (estimated to be costly because of long 1,600‑amp line runs) and a plan B to install a transfer switch to permit a mobile generator temporarily if FEMA funding does not come through. The committee voted to reallocate the existing $85,000 allocation (originally for Vernon Manor) to Vernon Acres so staff could sign agreements quickly should FEMA award the grant.
"We're proposing if the committee would approve it, using that $85,000 that was allocated for a generator in Manor, just using that for the generator at Acres," Amy Oliver said, describing the funding strategy and timeline. Staff indicated the state expects a decision in about three weeks but made no guarantee.