Committee seeks $40,878 increase for Highway 28 conductor‑casing contract; item moved to consent

Sewer and Water Committee · August 8, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction manager Phil Tapia told the Sewer and Water Committee that Change Order No. 3 reconciles bid estimates with as‑built quantities, asking the committee to increase the contract by $40,878 and place the item on the consent agenda.

The Sewer and Water Committee was asked to place Change Order No. 3 for the Highway 28 conductor‑casing project on the consent agenda after staff reported a small net increase to the contract.

"We're seeking authorization or, approval to, increase the contract amount at $40,878," said Phil Tapia, the construction manager, explaining the change order reflects final quantity balancing for paving, dewatering and rock removal compared with bid estimates. Tapia said the project is complete and the increase reconciles estimated quantities with as‑built numbers.

Committee members asked when the installed casing would be put into active use and whether other lines would be connected soon; staff said only one line is in service at Terrace at present and additional connections are expected further out. Committee members indicated support for placing the item on the consent calendar for the board meeting.