New water superintendent lays out schedule for treatment-plant replacement

City of Ellsworth Project Management Team · August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Erica, the new superintendent of the water department, presented a schedule for the replacement project: design-basis report due end of October, 60% design January 2027, 90% design end of March, bids late March/April, construction June 2027–October 2028; staff also described recent operational moves and a temporary office trailer near the plant.

Erica, the newly appointed superintendent for the water department, presented a multi-stage schedule for the replacement of the water-treatment facility and outlined near-term pilot testing and design milestones.

"I'm Erica. I'm the new superintendent for the, water department," Erica said, then walked through key dates: a design-basis report due at the end of October, 60% design in January 2027, 90% design at the end of March, bid set at the end of March and a bid opening at the end of April, with construction hoped to start in June 2027 and finish in October 2028. She also said a test well and pilot-plant work are scheduled this month to inform filter design and chemical treatment.

Why it matters: the schedule establishes procurement and construction milestones for a multi-year capital project that will affect water operations. Staff also noted steps to improve field oversight by placing a temporary office trailer at the treatment plant for closer operational monitoring. Next steps: continue pilot testing, finalize design milestones with the consultant and prepare bid documents.