Board authorizes guaranteed-maximum-price amendment for Reynolds High cooling-tower replacement

Reynolds School District Board of Education · March 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board voted unanimously March 18 to authorize a GMP amendment to proceed with replacement of the cooling tower at Reynolds High School; the motion was made by Director Ana Gonzalez Muñoz and seconded by Director Francisco Ibarra.

At its March 18 meeting the Reynolds School District Board of Education approved an authorization to proceed with a guaranteed-maximum-price (GMP) amendment for the cooling tower replacement project at Reynolds High School.

"I move that the Board authorize the district to proceed with the GMP amendment for the cooling tower replacement project at Reynolds High School," the motion language recorded in the minutes shows. The motion was made by Director Ana Gonzalez Muñoz and seconded by Director Francisco Ibarra and passed unanimously, Yea: 5, Nay: 0.

The minutes do not include contractor names, the GMP dollar amount, or a projected construction timeline. The item appears under Action Items as an approved capital project; the board did not record subsequent implementation steps in the minutes provided.