Committee to call for bids to replace Rubicon Tank No. 1 feed line to relieve system bottleneck
Summary
Senior civil engineer Will Stelter recommended calling for bids to replace about 350 feet of 6-inch feed line with a 10-inch line at Rubicon Tank No.1; engineer estimate just under $300,000 with $75,000 in grant funding; bidding planned for October and construction in 2025.
Get email alerts on the Rubicon Tank Feedline topic
No spam. Unsubscribe anytime.
The committee agreed to call for bids on the Rubicon Tank No. 1 water feed line replacement (Resolution 24-29), a project to replace roughly 350 feet of 6-inch piping with a 10-inch line to address a system bottleneck.
Will Stelter, senior civil engineer, said the work was identified as a constriction point and that the engineer's estimate is "just shy of 300,000." He added that the project will receive about $75,000 in grant funding and is scheduled for design completion and permitting ahead of an October bid and a November award, with construction slated for 2025.