Funding crunch could force phase cuts on West Shore Trail rehabilitation, staff warns
Summary
Staff told the committee that cost increases since the original grant application mean NTCA/Placer County funding of about $1,400,000 may not cover the full West Shore Trail scope; the district’s match requirement could rise from roughly 25% to nearer 50% unless partners increase awards or the project is downsized.
Get email alerts on the Trails Funding topic
No spam. Unsubscribe anytime.
Staff warned that the West Shore Trail rehabilitation scope and cost have changed since the district's multi‑year grant application, and partners are re‑evaluating year‑2 and year‑3 funding commitments. Staff said outside partners (Placer County and the North Tahoe‑Conservancy Authority) originally approved only year‑1 funding and that 'we have been told by Placer County and NTCA that they're willing to move forward with releasing year 2 funds' but that the project the district would now build looks different and costs have risen.
The committee heard a specific external funding figure and a funding‑match implication: staff said roughly $1,400,000 had been the previously anticipated partner contribution and that the district's required match could materially increase above the 25% level stated in the original submission. "All indications are we'll get the 1,400,000," a staff presenter said, but added that the district must be transparent about scope changes and may have to phase work or seek a larger partner award. Council members urged staff to negotiate with partners about adjusting the award or to present phased alternatives if partners cannot increase funding.