Council approves $2026 manhole repair contract after hearing on 76-site sewer project

Algona City Council · August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a public hearing on the 2026 sanitary sewer manhole improvements project covering 76 manholes, the council voted to award the construction contract to Moran's Ground And Excavating; staff listed the project estimate at $778,000 and the winning bid read at the meeting as '$745,000 $903'.

The Algona City Council opened a public hearing at 05:14 on Aug. 3 for the 2026 sanitary sewer manhole improvements project and later approved a resolution awarding the construction contract.

City staff described the project as rehabilitation, replacement and spot repairs of 76 manholes—concentrated in the city’s north and west sections—and listed the project estimate in meeting remarks as $778,000. Kevin Graves of WHKS Engineers said the work is intended to be done this fall and wrapped up by early December to address structural deficiencies.

At the July 30 bid opening the staff reported a single bidder, Moran's Ground And Excavating. In the meeting record the bid was read as "$745,000 $903"; staff recommended awarding the contract to that bidder and the council approved the resolution to do so.

The council’s vote was announced as carried. The staff said the contractor will coordinate required traffic control and any permitting for work near high-traffic State Highway 18 crossings. No public comments were filed on the hearing notice.

Why it matters: the project addresses sewer inflow and infiltration issues and structural defects in the city’s manhole infrastructure. The award will put construction crews into neighborhoods where traffic control and short-term lane restrictions are expected.

Next steps: the contractor and city will hold pre-construction coordination, including traffic-control plans for high-traffic segments; staff indicated anticipated work and reopenings in mid- to late-August and full wrap-up targeted for early December.