Flatwoods Middle School construction approved with $77.07 million guaranteed maximum price
Summary
The board approved Metcon's guaranteed maximum price (GMP) of $77,073,860.83 for Flatwoods Middle School construction and approved a change order to incorporate the GMP into the Metcon contract.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Finance and auxiliary services staff presented bid tabs and a guaranteed maximum price (GMP) for the Flatwoods Middle School construction project. Staff said Metcon had tabulated bids and proposed a GMP of $77,073,860.83 for the project; the board voted to approve the GMP.
Auxiliary services staff explained that the change order would modify the original planning services contract (originally $382,365) to include the construction GMP so that Metcon's contract covers preconstruction and construction services. A motion to approve the change order carried on voice vote.
Board members noted contingencies included in the GMP and the expectation that further change orders could follow during construction; no dissenting votes were recorded on the GMP or the change-order approval.