Summary

Jason Hahn of Jefferson PUD told the Port Ludlow Village Council about a cost-of-service/rate study, federal funding outreach, a public preparedness event Saturday at 2 p.m., and planned transformer relocations including installation of a 20-megawatt transformer at Quillsey to improve South County capacity.

Jason Hahn, representing Jefferson PUD, told the council the utility is pursuing federal funding opportunities and working through a cost-of-service and rate study; presentations and the supporting PowerPoint are posted on the utility’s website for public review. "My name is Jason Hahn, Jefferson PUD. I'm here to give you an update," he said, and encouraged residents to watch the hybrid study meetings online.

Hahn described a public emergency-preparedness event scheduled for Saturday at 2 p.m., which will include generator-safety demonstrations, solar and battery-backup information, an emergency-management booth and a transformer demo trailer. He also described a coordinated equipment plan to increase capacity across the district: "We're putting in a 20 megawatt transformer, into the enclosed sub, taking the 6 megawatt transformer, moving that to Discover Bay," and moving an oversized transformer to Hastings and Port Townsend as part of an orchestrated series of moves designed to relieve winter-peak constraints and support future South County development.