Ridgefield Park hears CSO Phase I progress and starts planning for Phase II bond

Village Board of Commissioners · February 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Consultants told commissioners Contract 1 is about 90% complete, surface restoration about 80%, and the Village has spent roughly $984,000 of a $6.42 million CSO program; Phase II is projected at $11.5–$12.5 million and would require a bond ordinance and public hearing.

Consultants from Suburban Consulting Engineers and Mott MacDonald updated the Ridgefield Park Board of Commissioners on the combined sewer overflow (CSO) Long-Term Control program on Feb. 5, saying Phase I is nearing completion while Phase II will require new financing.

Erin Abline and Rachel Dultz of Suburban Consulting Engineers and John Dening of Mott MacDonald told the board that Contract 1 is approximately 90% complete and surface restoration is about 80% finished, with restoration work to continue in spring 2026. The consultants reported the Village’s out-of-pocket cost so far is approximately $984,000 of an overall $6.42 million program. The group said permit obligations are tied to an April 1, 2025 permit date and that the Village agreed to execute its Long-Term Control Plan to satisfy regulator requirements.

Officials flagged a dirt pile on Bergen Turnpike tied to the contractor New Prince; consultants estimated removal would cost about $300,000, and Mayor Adam MacNeill asked the Village Attorney to draft a letter notifying New Prince that no further payments will be made until the material is removed. The board also discussed Phase II planning: consultants described two contracts (2A and 2B) with a total projected cost between $11.5 million and $12.5 million. Mayor MacNeill and staff were advised that Phase II will require adoption of a bond ordinance and a public hearing before proceeding.

The consultants emphasized permit and enforcement timelines but did not propose a funding source at the caucus; members signaled the need to follow the permitting schedule and to avoid jeopardizing the Village’s agreement with the New Jersey Department of Environmental Protection.