Council committee approves $122,000 contract increase tied to Park District change orders

Palatine Village Council · August 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told the Infrastructure committee a $122,000 increase to the guaranteed maximum price for a renovation project at 200 Wood Street is attributable to Park District change orders and parking-lot work; the Park District will reimburse the village, and roughly $37,000 of contingency remains.

The Infrastructure & Environment Committee reviewed an increase to the village's guaranteed maximum price (GMP) contract for a renovation project at 200 Wood Street. Staff characterized the increase (about $122,000) as necessary to accommodate Park District change orders and parking-lot work and said the Park District will reimburse the village for those costs under the contract arrangement.

Staff also said that, after the change orders and previously approved parking-lot work, approximately $37,000 remains available for miscellaneous items as the project nears completion. A committee member praised the project progress; the committee voted to place the contract increase on the consent agenda for council approval.