Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
County reports progress—and sand buildup—from heavy rains on Talleywash project
Summary
County manager said heavy rains brought 2–3 feet of sand build-up in culverts affecting the Talleywash project; crews performed cleanup and dewatering and staff said the project was roughly four to five weeks from completion.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Dustin updated the board on work at the Talleywash project, reporting heavy rains had caused about 2–3 feet of sand accumulation under culverts and required cleanup and road rebuilding in places.
He said crews cleaned out culverts, performed dewatering for grouted riprap placement and expected the project to be about four to five weeks from completion. Supervisors received the update and did not make additional funding commitments during the discussion.

