Council OKs wastewater easements and temporary pump-and-haul memorandum; developer pays costs
Summary
Council approved easements to document existing wastewater lines and a memorandum allowing temporary pump-and-haul while a lift station is completed; staff and developers said the developer would bear the expense and expected about weekly 7,000-gallon truck trips to a nearby tie-in.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council approved the creation of easements to document existing wastewater force mains crossing development parcels and authorized a memorandum of understanding that allows temporary pump-and-haul while the developer addresses lift-station timing and FEMA-related floodplain issues.
Staff explained the lines were already present but lacked recorded easements and recommended formal easements to protect infrastructure and future permits. The developer's attorney and representative described pump-and-haul logistics and costs; a representative said, "We're usually looking at 7,000 gallons for the number of homes that they would want an early release for," and that the developer would bear the expense rather than the city.
City staff said permits and inspections would remain leverage points if issues arise, and council voted to approve the easements and the MOU. Staff and the developer noted pump-and-haul is typically temporary and used when construction timing or floodplain constraints delay permanent infrastructure. The agreement includes assurances that the city will not incur the pump-and-haul expense and retains permit/inspection authority.