Council approves $113,128.22 change order for Sports Park Center natatorium and ADA work
Summary
Council approved Change Order No. 14 for the Sports Park Center to add roughly 180 sq ft for ADA compliance and to correct ductwork and lighting raceway issues in the natatorium; staff said roughly $3.5–4.0 million remains in contingency and the project is about 75% complete with a likely summer opening window.
Get email alerts on the Sports Park topic
No spam. Unsubscribe anytime.
Brett Quarles (speaker 9) described Change Order No. 14 for Sports Park Center, which includes an approximately 180-square-foot addition to meet ADA requirements and corrective work in the natatorium to replace lighting raceways and add whips where ductwork clashed with lighting. The change order amount on the record was $113,128.22.
Council members asked about remaining contingency and project timing. Staff said between about $3.5 million to $4.0 million remained in contingency and that the project is approximately 75% complete; no firm completion date was given beyond a general target of sometime in the summer. The council moved, seconded, and approved the change order 6–0.
Questions and answers focused on ensuring compliance with codes in the natatorium wiring and on-site schedule coordination; staff said the prior light installations required replacement of raceways to meet code.