Council rejects EQ digester recoating bids after proposals exceed estimate
Summary
Public Works staff recommended rejecting bids for the EQ digester recoating project after two bids came in well above the engineer's estimate; council voted 7–0 to reject the bids and staff will review the project for re-bid or redesign.
Get email alerts on the Wastewater topic
No spam. Unsubscribe anytime.
Steven, presenting for Public Works, told council that the EQ digester recoating project received two bids on June 11; the low bidder was Wabasha Construction at $1,723,000 and Champion Coatings bid $2,369,000 — significantly above the department’s engineer estimate of $1,300,000. "Wabasha construction was the low bidder at $1,723,000," Steven said, and recommended rejecting all bids and reviewing the project again later.
Council moved and seconded the recommendation to reject bids; a roll-call vote recorded unanimous approval and the resolution passed 7–0. The department said it will reexamine scope, cost assumptions and timing before bringing a reworked solicitation back to council.
Why it matters: the wastewater-treatment expansion is one of the city’s largest capital projects; higher-than-expected contractor pricing can delay schedules or require scope adjustments.