MSD sewer work planned on Pembroke with tunneling under Watson, board informed
Summary
The Metropolitan Sewer District is set to proceed with a sewer project on Pembroke that includes tunneling under Watson and excavation from Watson to Heege; trustees were informed at the work session.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Chairman Bornmueller told trustees the Metropolitan Sewer District (MSD) will proceed with a sewer project on Pembroke that includes tunneling under Watson and street excavation from Watson to Heege. The work was presented during the Nov. 4 work session and reported to the board at the regular Nov. 12 meeting.
The minutes do not list a start date, duration, or funding responsibilities; trustees were informed of the planned scope so they could anticipate roadwork and potential disruptions to residents along Pembroke, Watson and Heege.