City engineer says Roosevelt and 8th Avenue work should allow through traffic by mid‑August
Summary
City engineer updated the council on 8th Avenue and Roosevelt intersection work: railroad planks are in, asphalt placed east of Roosevelt, concrete work is underway and the contractor anticipates restoring through traffic by August 17 or sooner for the start of school.
Get email alerts on the Streets topic
No spam. Unsubscribe anytime.
City Engineer Leif reported progress on the 8th Avenue corridor and the Roosevelt intersection that has been closed for reconstruction.
Leif said the railroad installed crossing planks, asphalt was placed east of Roosevelt, and concrete work for the Roosevelt intersection has begun with curing timelines to follow. "The contractor has started work on the concrete for Roosevelt itself... The anticipated schedule from the contractor was 2 weeks... We hope to see it open sooner," Leif said. He added the goal is to have through traffic restored by August 17 prior to school starting.
Council members asked follow‑up questions about curing time and staging; staff said sampling and cylinder testing would guide any earlier openings.