Townwide water main replacement work to begin May 6 in South Cle Elum
Summary
Town staff reported that pipe and equipment have been staged east of Town Hall and digging for the TownWide Water Main Replacement Project will begin Wednesday, May 6, 2026, along South Cle Elum Way; Fury Site Works is on site for utilities work.
Get email alerts on the Water Main Replacement topic
No spam. Unsubscribe anytime.
Superintendent Matt reported that materials and equipment for the TownWide Water Main Replacement Project have been staged on lots east of Town Hall and that excavation and pothole-digging for utilities will begin on Wednesday, May 6, 2026 along South Cle Elum Way. The contractor Fury Site Works is on site with equipment, including a Vactor truck, and has started initial pothole work.
The superintendent also reported routine public-works activity: most town rights-of-way have been mowed, park hosts are in place and the wells will be started next week. The minutes note no formal council vote on the water project at this meeting; the entry records operational status and upcoming construction start dates.