Taos County OKs $1.02 million contract to replace Rio Chiquito bridge
Summary
The county approved Contract TCC2025-59 to replace Rio Chiquito Bridge (no. 7760), awarding the work to GME Emulsions for $1,024,307.38 (inclusive of tax). The award passed on a roll call vote after a brief presentation by Public Works.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Deborah Chavez presented Contract TCC2025-59 for the Rio Chiquito Bridge project (bridge number 7760) and reported the inclusive contract amount of $1,024,307.38. The presentation described the contractor's scope (labor, materials, equipment and traffic control for removing and replacing the existing bridge) and noted the project will proceed under the advertised contract terms.
Commissioner Brush moved to approve the contract award to GME Emulsions and the commission approved the motion by roll call. "The amount inclusive of tax is $1,024,307.38," the presenting staff member stated during the contract presentation.