Facilities staff report progress on floor work, ceilings and HVAC
Summary
Facilities staff told the board summer crews and contractors have been stripping and waxing floors, installing ceilings and moving forward on HVAC ductwork and balancing, with some spaces already looking improved.
Get email alerts on the Facilities Update topic
No spam. Unsubscribe anytime.
Facilities staff updated the board on summer projects: floors that had not been stripped in years are being stripped and rewaxed, ceiling grids are being installed and HVAC ductwork is completed with balancing and programming to follow. Staff said professionals trained summer helpers on proper stripping and waxing techniques, and visible improvements were reported in several rooms after initial passes.
Board members thanked staff for the progress and noted remaining work — finishing ceiling grids, grill installation and fire-alarm calibration — that is scheduled in the coming days. The board recognized that the project timeline remains tight but expressed appreciation for the visible improvements so far.