Albert Lea council hears recreation facility update, contractor dispute over fire-alarm costs
Summary
City staff said the arena, aquatic center and splash pad projects are nearly complete but the arena exceeded budget after drainage work, rink-floor replacement, a temporary chiller and a required new fire-alarm system; the city has demanded the general contractor cover the alarm cost and is prepared to pursue claims.
Get email alerts on the Recreation Facilities topic
No spam. Unsubscribe anytime.
Kathy Malakowski, the staff presenter for the recreation facilities program, told the Albert Lea City Council on July 27 that the city has essentially finished a multi-part capital program covering the city arena, aquatic center and splash pad, but that the arena portion ran over budget because of unexpected drainage, a replaced rink floor and a new fire-alarm requirement.
"The actual expenses for the arena came in at about 11,096 thousand," Malakowski said, noting the city budgeted roughly $10,000,010 and is now estimating an overall program cost of about $12.7 million across projects. She described specific savings and overruns on the aquatic center and splash pad and said the current net estimate shows the program close to budget overall.
The city attorney told the council the city has made a written demand on the general contractor to reimburse the city for the additional fire-alarm costs. "We've made a demand to the contractor to address the cost overrun and specifically demand compensation for the additional costs that we were forced to bear in order to mitigate our damages," the city attorney said, adding the contractor has so far declined to accept responsibility and the city has identified contract language it believes obligates the contractor to pay.
Malakowski outlined causes for schedule extension and cost increases: substantial drainage work at the arena site, a cracked/heaving rink floor that required replacement, a temporary chiller rental while refrigeration was delayed, and the discovery during expansion that the existing alarm panel lacked capacity and required a full upgrade. She also said staff located local contractors who could complete necessary alarm upgrades at lower cost than the contractor's initial demand.
On funding, the city plans to apply for roughly $2.5 million in federal incentives under the Inflation Reduction Act; Malakowski said the city has retained Deloitte LLP to prepare the incentive filings. She reported a revised completion date of July 31, 2026 for the arena elements, up from an original Nov. 14, 2025 target, and said staff had extended some warranties (Total Mechanical extended a floor warranty to three years in writing).
Council members thanked staff for work managing the projects and asked technical questions about drainage outfalls and remaining punch-list items. Malakowski closed by listing remaining tasks — roof repairs, sealing a lobby window, reverse-osmosis leaks affecting ice production, and software updates — and said staff will continue post-completion monitoring and outreach to user groups. "In summary, I would just say we fulfilled the city's mission of delivering exceptional services," she said.
What happens next: staff will pursue the contractor claim, finalize remaining repairs and submit federal incentive applications; the council did not take any new policy action on the items during the meeting.