Summary
Officials described early talks with a developer about a phased solar project on roughly 1,200 acres along South 85 Highway that could bring approximately $500,000/year in lease revenue on a 25‑year lease; soil/geotech and anchoring challenges and possible battery storage or gas plant options remain to be evaluated.
Get email alerts on the Renewable Energy topic
No spam. Unsubscribe anytime.
President (speaker 2) told the council there is developer interest in a multi‑phase solar project on the South 85 Highway with potential city lease revenue "somewhere around a $500,000 a year for the lease" under discussion for a 25‑year lease. Staff cautioned the project is at an early stage and requires geotechnical testing because the rocky soil may affect anchor installation for panels.
Councilors also discussed complementary energy proposals including industrial lithium‑ion battery storage to smooth supply and a possible natural‑gas peaker plant on an unnamed corner of the ranch. Staff emphasized the proposals are preliminary: developers have requested testing and there are several technical and permitting issues to resolve before the city can expect lease revenue. The council did not take formal action but asked staff to continue follow‑up and due diligence.