Utility staff report filter work finished and tower progress; Community Crossings grant application upcoming

Lakeville Town Council ยท August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Utility staff told the council filter media replacement on two tanks finished July 14, generators will be serviced in the fall, fence posts for a new tower are in place and the Community Crossings grant application window opens Sept. 1.

Utility staff reported that work on filter media for two tanks finished on July 14 and the systems are performing normally. On generator maintenance, staff said the town is scheduling service in the fall and that Cummins identified two complimentary services for the filter-plant generator based on paperwork: "there are 2 free services," the staff said, which will reduce the town's immediate costs for that unit.

Staff also updated the council on the Community Crossings grant, noting the grant opens Sept. 1 and that the town has sent road data to a paving company to get budget estimates ahead of the application. On communications infrastructure, staff said fence posts for the tower are mostly set and concrete work was tentatively scheduled to start on Thursday (date not absolutely certain in the transcript). They also described monitoring measures after a cybersecurity inquiry: controller systems will issue alerts but cannot be used to change plant controls, and Peerless will send alerts for unusual activity.