Hollow Park restroom delayed to end of June after unforeseen septic issue

Board of Selectmen, Town of Woodbury · May 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Officials said construction of a family restroom at Hollow Park is delayed after crews discovered the expected septic cleanout was actually a shutoff valve; the project now includes excavation and trenching and the completion target moved from end of May to end of June.

Construction of a family restroom at Hollow Park, originally targeted for completion at the end of May, has been delayed after contractors found an unexpected issue with the septic connection.

The 1st Selectman said what was believed to be a septic cleanout was discovered to be a shutoff, requiring cutting the floor and excavating a trench to access the septic pipe. He told the board the revised completion estimate is now the end of June.

The board did not vote on additional funding at the meeting; the 1st Selectman said staff will manage the added work and report back as needed.