Engineer updates: Wolf Road paving scheduled; Perry drainage complete; ADA ramp bids under budget
Summary
The borough engineer said Wolf Road milling and paving will be completed in a short, scheduled closure, reported completion of Perry Street phase 2 drainage, and presented low bids for Central Avenue ADA ramps (low bid $13,292.50) with work planned before the school year.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Tom, the borough engineer, updated the council on multiple public-works projects: Wolf Road’s remaining milling and paving is scheduled for a short, single-day closure; the Perry Street drainage project (phase 2) is complete and a change order covering final payment was on the consent agenda; and municipal road paving is essentially finished with minor punch-list work remaining.
Tom also reported two quotes for Central Avenue ADA ramps with Angels Construction submitting the low bid of $13,292.50; he recommended moving ahead so the ramps could be completed before schools reopen. Council members asked about brief closures, striping status at the library parking lot and contractor coordination; the engineer said contractors would address punch-list items during a planned visit.