Anderson Burton outlines GMP approach; Stage 1 $1.8M, base construction ~ $15.6M with $2.3M alternate

Avalon City Council · April 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Anderson Burton and RM Design described a progressive design‑build delivery, open‑book budgeting and sample costs (Stage 1 $1.8M; Stage 2 base ~$15.6M; alternate ~$2.3M). The team stressed logistics, seaworthy structural choices and long‑term maintenance planning.

Tim Merrill, CEO of Anderson Burton, presented the contractor's progressive design‑build/GMP method and said the team would work with the city in an open‑book fashion to validate costs. "We will give you all our hours, our costs, everything, and compare it to the bids we got," Merrill said, describing bid leveling and transparency measures intended to avoid scope gaps and unnecessary change orders.

RM Design principal Mike Scott described the team's coastal design experience and a focus on longevity: a 75‑year building life, tsunami‑resistant structure and choices to reduce exposed metals that require recurring coating maintenance. The team proposed block/CMU at the ocean‑facing side with structural steel support where necessary to resist wave forces.

Anderson Burton presented preliminary numbers: Stage 1 (design initiation and GMP development) at $1.8 million; Stage 2 base scope around $15.6 million; and an alternate scope at $2.3 million that could be lowered if bid as part of the final GMP. Merrill cautioned these are working estimates and that early procurement and design choices would shape final pricing.