Staff reports Progress Park data center plans approved; connector road due late 2027
Summary
County Engineer and staff said plans for a proposed data center at Progress Park were approved and that the Progress Park connector road is expected to be finished by late summer/early fall 2027; VDOT and sewer/water updates were also given.
Get email alerts on the Progress Park Development topic
No spam. Unsubscribe anytime.
County Engineer Johnny Kincer briefed the commission that his office approved plans for a proposed data center at Progress Park and that he is currently working on pond work at the Hitachi Energy Arena.
Deputy County Administrator Matt Hankins provided a timeline for county infrastructure supporting Progress Park, saying, "The Progress Park connector road; it should be finished by late summer/early fall of 2027." He also summarized local VDOT projects including proposed additional climbing lanes toward Bland and an aligned four‑way intersection project at the former Italian Garden location on Monroe Street, and reported that the new northbound I‑77 entrance is open while southbound work continues.
Hankins said the county’s Route 52 sewer project is up and running and that the Water Department is pursuing a larger pump station for Siloam and Shadow Lane to serve increased housing and larger pipe needs. The updates were presented for informational purposes; no formal action was taken at the meeting.