Staff: Lark Avenue paving nearly complete; bridge B60 and Thrush scheduling remain
Summary
County staff reported Lark Avenue paving should finish this week if weather cooperates, while bridge B60 has no current progress and Thrush Avenue letting this month makes summer construction unlikely. A Rockwell Building preconstruction meeting is being scheduled.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Brandon, speaking for county staff, said "Lark Avenue paving is going on out there right now" and that, if weather holds, the pavement itself should be completed this week though shoulders and striping will follow before the road is reopened.
Staff also reported no current progress on bridge B60; work on that bridge is expected toward the end of winter when contractor availability allows. On Thrush Avenue, staff said the project letting is this month and that, given the timetable, construction is more likely in spring than this summer. A preconstruction meeting for the Rockwell Building is being arranged and staff expected an update the following week.