Board reviews Measure J plan: start construction summer 2026, Phase 1 focused on seismic work

Sunol Glen Unified School District Board · December 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architects and contractors outlined a phased Measure J renovation: Phase 1 (seismic mitigation, roof, structural work) estimated at about $6.0M, Phase 2 finish work about $3.0M; about $7.0M in Measure J funds are available for Phase 1 and board discussed a possible bridge loan while awaiting state funds.

District consultants presented a phased construction plan under Measure J focused on seismic mitigation to make the main building safe for occupancy. The presenter said Phase 1 would include abatement, demolition, structural concrete and steel, roof replacement, sprinkler and rough plumbing, and preparation for later HVAC and finish work. "Phase 1 includes all of the seismic mitigation work on the project," the presenter said.

The team recommended starting construction in summer 2026 and bringing a Guaranteed Maximum Price (GMP) for Phase 1 to the March 10 board meeting. The presenter reported approximately $7,000,000 in Measure J funds available for Phase 1 and a Phase 1 estimate in the $6.0M range, with Phase 2 estimated at roughly $3.0M. The board discussed bridge financing options to cover cashflow while awaiting state seismic apportionments and FEMA reimbursements and weighed risks including stalled work if external funds do not arrive.