Belvedere awards $3.51 million Beach Road seawall contract; council reallocates CIP funds to close a $310,000 gap

Belvedere City Council · April 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council awarded the Beach Road Stabilization Project contract to Gordon N. Ball Inc. for $3,511,620. Staff identified a $310,000 funding gap and proposed reallocations from Measure AA, road impact fees and CIP rollovers to preserve an approximate 11% contingency and pursue a June 1 start if permits arrive.

The council voted to award the Beach Road Stabilization Project construction contract to Gordon N. Ball Incorporated, the lowest responsive bidder, at $3,511,620. Staff said the bid exceeded the project estimate by roughly $310,000 and identified four CIP funding sources totaling $345,000 to cover the gap and maintain a construction contingency of about 11%.

Project staff outlined the proposed reallocations: $125,000 from Marin Measure AA allocations, $33,000 from the city road-impact fee fund for paving restoration, $172,000 from a retaining-wall repair CIP rollover, and $15,000 from a sidewalk-repair rollover. Tony, the public-works representative, noted that some permits — including BCDC and Army Corps approvals — and coordination with PG&E remain outstanding; if permits come through, construction could begin June 1 and run through the contractor's October 30 window.