Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Sewer Infrastructure topic

No spam. Unsubscribe anytime.

Engineer outlines lining and replacement options for Plevna’s clay sewer mains

Plevna Town Council · January 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project engineer described two repair strategies for the town's mainly clay-tile sewer mains — open-cut replacement with PVC or cured-in-place lining (CIPP) — and said the PER will identify which approach fits each section based on camera footage and manhole condition.

At a Jan. 28 public meeting, Brosz Engineering’s project engineer described two common approaches to rehabilitating Plevna’s largely clay-tile sewer mains: open-cut replacement with PVC and cured-in-place pipe lining (CIPP).

"Or 2) do what's called a CIP (cured in place pipe). With that it's actually felt that is soaked in resin and they blow it through the pipe and then they run stieve or hot water through it to cure it and then it's like a brand new pipe," said Rylan Limesand, describing the lining process and its structural intent. The engineer said the town’s existing camera footage will help determine where lining is feasible and where full replacement or manhole rehabilitation will be required; he added the PER will design liners to a specific design life.