Consultant flags thin owner contingency: PCOs, propane tanks and possible BDA system will draw from contingency

Regional School District 13 Building Committee · August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

STV reported approximately $400,000 in PCOs (offset by value-engineering) and an owner contingency balance trending at about $216,000; consultants listed potential placeholder costs including eight propane tanks ($5,000 each), piping, a small water tank and a $76,000 BDA radio system alternate.

STV presented a financial snapshot showing the effect of recent value-engineering and ongoing change items on the project's owner contingency.

"Your owner contingency balance is trending at only $216,000," the consultant reported, adding that the PCO log shows roughly $400,000 in potential change orders before offsets and value-engineering. The consultant listed several placeholder items: eight propane tanks at $5,000 each (about $40,000), $20,000 for piping between tanks and building, a $2,400 water storage tank and a $76,000 allowance for an in-building radio amplification (BDA) system.

Staff noted the geotechnical finding that fractured shale below the addition may require crushed stone under foundations; a placeholder of about $50,000 is in the log pending final testing and pricing. Committee members asked for tighter vetting before numbers hit decision tables and emphasized the need to refine the PCO tally.