Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Construction Progress topic
No spam. Unsubscribe anytime.
Memorial School renovation on track despite steel delay; contractors plan weekend work
Summary
Contractors reported ongoing site and foundation work for the Memorial School addition and said a late steel shop-drawing submission pushed Area F and G back toward mid-September; the team plans overtime and Saturday shifts to recover schedule.
Get email alerts on the Construction Progress topic
No spam. Unsubscribe anytime.
Contract and design teams told the Regional School District 13 Building Committee that sitework, foundation excavation for Areas F and G and interior framing are ongoing and that the concrete contractor mobilized this week.
"Within the next 2 weeks, we'll start digging for the gym edition," said Howard Weisberg, who led the update for the building team. Staff reported temporary power hookups and the disconnection of existing service are in progress, rebar is arriving and concrete forming for the gym and classroom addition will begin once materials are onsite.
Consultants flagged a schedule slip caused by a late steel subcontractor submission. To recover, contractors said they will start Saturday work and use targeted overtime while coordinating steel deliveries and shop-drawing sign-offs. "We're gonna try our best to recover in the next few months," a project representative said during the update.
The committee asked for a recovery plan from the steel contractor and regular updates to monitor the critical path. No formal schedule change was adopted at the meeting; staff said they would continue to track progress and report back.

