Board approves $6.68M early procurement GMP for structural steel despite Phase 1 funding gap

Sunol Glen Unified School District Board of Trustees · March 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board approved an early-procurement GMP of $6,682,497 for structural steel to secure materials now, while Measure J consultants said Phase 1's full GMP (about $8.04M) exceeds available Phase 1 funds and a roughly $3.9M funding gap remains for the main building.

The Sunol Glen Unified School District board approved an early-procurement guaranteed maximum price (GMP) for structural steel to support the Measure J main-building seismic upgrade, with a fiscal impact of $6,682,497 charged to fund 21.

Phil Savage, the bond implementation consultant, told the board that Landmark Constructorss initial Phase 1 subcontractor price was $8,043,495 and the districts available funds for Measure J stood around $7,845,576, leaving a "delta" of roughly $3.9 million for the main building. Savage said the district is working with Landmark to lower Phase 1 costs, move some scope into Phase 2 and seek a state funding match or bridge loan to bridge the shortfall. "The phase 1 here is 8,043,495," he said during the presentation.

Trustees discussed best-value scoring of steel subcontractors, workforce-certification requirements under Education Code provisions for lease-leaseback projects, and the need to keep lease terms governing any exclusions. Board members approved the early-procurement GMP so the district can secure steel now amid volatile materials prices; Savage said the early procurement is a preconstruction action and that no DSA-required work will occur before approvals. Staff warned the board they may need a special meeting in late March if further contract revisions are required.