Council approves $5,005.64 payment for Felicity substation control panel upgrade
Summary
The council approved a $5,005.64 payment to Swartzard Engineering Laboratories for work replacing a locked-up control panel at the Felicity electrical substation; staff said parts are no longer available for the old model and the city will upgrade the panel.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Under Item 9 staff explained a control panel at the Felicity substation locked up; an electrical engineer diagnosed the issue and the city ordered a replacement because parts for the older model are no longer available. The council approved payment of $5,005.64 to Swartzard Engineering Laboratories to secure the replacement panel and avoid future outages.
A council member thanked staff and the electrical superintendent for addressing the outage and for ordering the replacement so the city has the part on hand when it arrives.